Last April Update (4/27)

Posted by & filed under bladeRF.

  This past week was rather uneventful. As we continue to wait for the boards to get assembled we’ll update the FPGA, firmware, drivers, and user mode applications. We are also working on finishing up our order fulfillment system so we can start taking your mailing addresses.

Weekly update (4/19)

Posted by & filed under bladeRF.

  This week was pretty exciting, we were dropped off 4 large boxes full of components at the assembly house in San Francisco (scroll down for pictures). The custom RF shields also showed up, and it looks as if they will fit perfectly! At this point, we’re waiting on word from the assembly house for… Read more »

Weekly update (4/12)

Posted by & filed under bladeRF.

  We were able to get revised delivery dates for all of our components this past week. We will have everything we’ll need for the mass-production run by the first week in May, so mass production is likely to be done in the later half of May. Pre-production is also on schedule. We’re working with… Read more »

April Update

Posted by & filed under bladeRF.

  So we have received most of the components needed for the pre-production run (scroll down to see)! There were a few issues with some of the components not arriving in tubes or on reels, so we are working on getting them replaced in the next few days. The custom RF shields and factory programmed… Read more »